Weekly status report template: the project status report on one page.

A short report, on the same day each week, that tells the client what moved, what's next, and what depends on them. Download the spreadsheet with the filled-in example or build the report from your Tasskee data.

Example: Casa Serrana online store, week of Sep 22-26 Download it as a spreadsheet (opens in Excel and Google Sheets) or build it right in Tasskee, with deadlines, assignees and notifications.
Download spreadsheet Use it on Tasskee, free
BlockWhat to writeExample
ResumeThe overall status in one sentence, with the traffic-light colorGreen: project on schedule, Oct 10 delivery maintained
ResumePercent complete and the expected finish date62% complete; expected finish on Oct 24
Delivered this weekWhat's done, in the client's languageProduct and cart pages published in the test environment
Delivered this weekWhat the client approvedHome page layout approved by Marta on Sep 24
Next weekWhat will be done and who is doing itPIX and card payment integration (Thiago); registration of 120 products (Aline)
Next weekWhat the next client-visible deliverable isFull checkout demo on Friday, Oct 3
Risks and blockersWhat could slip and what's already blockedRisk: payment provider approval takes up to 5 business days
Risks and blockersWhat was done to reduce each riskApproval request submitted on Sep 25, ahead of schedule
Pending client decisionsWhat the client needs to decide and by whenChoose free shipping above R$ 200 or R$ 300, by Sep 29
Pending client decisionsWhat the client needs to sendPhotos of the 40 products still missing images, by Sep 30
MetricsCompleted and pending tasks28 completed, 17 pending, 2 overdue
MetricsHours spent vs. planned212 h spent of 340 h planned (62%)

What is a weekly status report

The status report is the report that answers, at the start or end of every week, the question the client is always thinking: "how is my project going?" It fits on one page and always has the same blocks: summary, what was delivered, what comes next, risks and blockers, pending decisions and a few metrics.

When the report goes out on the same day every time, the client stops chasing you by message. And when it goes out with the problems written down, nobody is caught off guard on the delivery date.

How to fill it in, block by block

BlockWhat to writeCommon mistake
SummaryOne sentence with the situation and the color: green (on schedule), yellow (attention) or red (behind)Writing a paragraph and leaving the client to work out the situation
Delivered this weekWhat got done, in the client's language, and what they approvedListing technical tasks the client doesn't understand
Next weekWhat will be done, who does it and what the next visible deliverable isPromising more than fits in the week
Risks and blockersWhat could cause delay, what has already stalled and what's being done about itLeaving out the risk so as not to worry the client
Pending client decisionsWhat they need to decide or send, with a deadlineLeaving the pending item buried in the middle of the text
MetricsCompleted and pending tasks, delays and hours against planFilling it with numbers nobody uses to make decisions

Step by step to write the report

  1. Pick the day and stick to it. Friday afternoon or Monday morning, always the same. Regularity matters more than perfection.
  2. Start with the summary. Write the color and the sentence last, after you know what happened, but leave them at the top of the page.
  3. Write the client's pending items with a date. "I need the photos by Wednesday" prompts action; "photos are missing" prompts a conversation.
  4. Pair each risk with an action. A risk without a response plan is just worry.
  5. Send it through the same channel. Email, portal or PDF, but always the same, so the client knows where to look.

Common mistakes in the status report

  • A traffic light that's always green. If every report is green until the day of the delay, the client stops trusting the color.
  • A report that's too long. Past one page, nobody reads it. Put the detail in an attachment.
  • Hiding the pending decision. The biggest cause of delay in service projects is the client being slow to respond, and the report should make that visible, without blaming.
  • Typing everything by hand. Completed tasks and hours already exist somewhere. Whoever copies them manually spends an hour a week and still makes mistakes.

When the template isn't enough

The status report tells what happened, it doesn't predict what's coming. To see the effect of a delay on the following stages, use a project schedule, or the Gantt chart, which links one task to another. And when the client needs to record that they approved a deliverable, the report doesn't replace a delivery acceptance form.

The report that comes out ready

In a spreadsheet, someone pulls the numbers together every Friday. In Tasskee, completed tasks, overdue tasks and hours come from the project's actual progress.

See the reports

How to use the status report in Tasskee

  1. Keep the project up to date: tasks with an assignee, due date and status. That's where the "delivered" and "next week" lists come from.
  2. Filter the tasks completed this week and those due next week, and copy the titles into the report.
  3. Use reports and dashboards (Pro plan) for task and hours metrics, instead of counting by hand.
  4. Record pending decisions as tasks assigned to the client, with a due date, and let them follow along through the guest portal, where they comment and approve.
  5. If you want the client to receive the report without you writing it, the portal already shows the project's progress at all times, and the weekly report becomes a summary, not the only source.

Want the template for bringing a client on board? See the onboarding checklist. For other templates, open the free templates hub.

Frequently asked questions

Status report FAQ

What is a project status report?
It's a short, periodic report that tells the project's status: what was delivered, what's next, what could slip, and what depends on a decision. The weekly version is the most widely used on service projects.
What's the ideal length for the report?
One page. The person reading a status report is a client or executive short on time. If the report needs more room, the extra goes in an attachment or a meeting, not the body.
Weekly or biweekly?
Weekly is the standard for projects of up to a few months, because a problem can grow a lot in two weeks. For long, stable projects, biweekly is usually enough. What matters is regularity, on the same day and time.
Should I show the client the problems?
Yes, with the action plan alongside. A client who discovers the delay from the delivery loses trust; a client who gets an early heads-up, with a proposal, usually helps solve it.
Can I generate the status report without typing everything?
Yes. In Tasskee's Status Report you choose the template, the projects, and the period: the metrics come from real progress, the AI writes the sections from them, and you review and export the PDF. This spreadsheet template is for those who are just getting started.

Generate the status report from real progress.

In Tasskee, the report comes from the project data, the AI writes the sections, and the PDF is ready to send. Try it free, no credit card.

15 days with everything unlocked No credit card Support in Portuguese
Contact us