Construction schedule template: a free spreadsheet with a renovation example.
From demolition to final cleaning, each task with a deadline, dependency, and assignee. Download the filled-in spreadsheet or track the job in Tasskee's Gantt.
From demolition to final cleaning, each task with a deadline, dependency, and assignee. Download the filled-in spreadsheet or track the job in Tasskee's Gantt.
| Stage | Task | Home | End | Duration | Depends on | Responsible | % complete |
|---|---|---|---|---|---|---|---|
| Preliminaries | Protecting areas and demolishing wall and floor coverings | 06/10 | 10/10 | 5 days | - | Mr. Antônio's crew | 100% |
| Preliminaries | Debris removal | 13/10 | 14/10 | 2 days | Demolition | Mr. Antônio's crew | 100% |
| Utilities | Plumbing pipes and water points | 15/10 | 21/10 | 5 days | Debris removal | Hidráulica Souza | 80% |
| Utilities | Wiring and electrical panel | 15/10 | 23/10 | 7 days | Debris removal | Electrician Fábio | 60% |
| Masonry | Patching wall chases and plastering | 24/10 | 30/10 | 5 days | Plumbing; electrical | Mr. Antônio's crew | 0% |
| Waterproofing | Bathrooms and laundry area (with 72-hour test) | 31/10 | 05/11 | 4 days | Plastering | Impermeabilizadora Sul | 0% |
| Wall and floor coverings | Subfloor screed and porcelain tile installation | 06/11 | 19/11 | 10 days | Waterproofing | Tiler Cláudio | 0% |
| Drywall | Drywall ceiling and cove molding | 20/11 | 26/11 | 5 days | Electrical wiring | Drywaller Wilson | 0% |
| Carpentry | Final measurements and cabinet installation | 27/11 | 08/12 | 8 days | Wall and floor coverings | Marcenaria Pinheiro | 0% |
| Painting | Skim coat and two coats of paint | 27/11 | 05/12 | 7 days | Drywall | Painter Ricardo | 0% |
| Finishing | Fixtures, faucets, outlets, and light fittings | 09/12 | 12/12 | 4 days | Painting; carpentry | Electrician Fábio | 0% |
| Delivery | Final cleaning and walkthrough with the client | 15/12 | 16/12 | 2 days | Finishing | Carolina (architect) | 0% |
A construction schedule is the sequence of services in a build or renovation, with dates, duration, assignee and the order in which each can happen. It exists because construction has a trait few projects have: the services physically depend on one another. The drywall waits for the wiring, the painting waits for the drywall, the flooring waits for the waterproofing to dry.
The template above shows the renovation of a 70 m² (about 750 sq ft) apartment, in twelve services. For a house or a commercial renovation, the structure is the same: swap the services, the deadlines and the assignees.
| Column | What to write | Common mistake |
|---|---|---|
| Stage | The service group: preliminaries, utilities, finishes, painting, handover | Mixing stage and service in the same column |
| Service | The concrete work, with the location when it matters: "waterproofing of the bathrooms" | Describing only the material, without saying what will be done |
| Start and End | Real calendar dates, in the format 06/10 | Counting Saturdays and holidays as workdays without agreeing on it |
| Duration | Working days for the service, provided by whoever does it | Forgetting curing, drying and testing time |
| Depends on | The service that has to finish first | Leaving it blank: two services "in parallel" in the same room get in each other's way |
| Assignee | The crew or professional responsible for the service | Not having a name to hold accountable |
| % complete | Actual progress, in simple increments (0%, 25%, 50%, 100%) | Reporting an optimistic number without checking on site |
A spreadsheet gives a good snapshot of the plan. It doesn't show the knock-on effect: if waterproofing slips three days, the flooring, the carpentry and the handover slip too, but the dates in the table stay the same until someone changes them. A Gantt chart with dependencies does that calculation visually, and the Gantt chart guide explains the critical path, the sequence of services that really determines the end date.
Mind what this template doesn't do. It controls schedule and sequence. Budgeting, cost breakdowns, service measurement and the site log are another kind of system, construction ERP, and Tasskee doesn't replace that. It organizes the schedule, the tasks and the communication between crews. Anyone managing construction jobs at an engineering firm can see how this works on the for engineering and construction page.
In Tasskee, each service is a task with an assignee and a due date, linked to the others in the Gantt. If a date changes, you see what changes along with it.
See the Gantt scheduleTo build the deadline plan with more method, also see the project schedule template and the work breakdown structure (WBS), which help break the job into work packages before putting dates on them.
What it is, where it comes from, dependencies, the critical path with a numeric example, and a step-by-step guide to building your own.
ViewStages, deadlines, assignees, and dependencies, with a system implementation example.
ViewDeliverables and work packages with a code, assignee, and definition of done.
ViewSchedule with dependencies, a workstream per phase, and signed sign-off with a photo.
ViewDeadlines, dependencies and milestones on a timeline the team understands.
ViewDrag the task to another column and the whole team sees the progress.
ViewTasks linked by dependency, assignees, and status on the same screen. Try Tasskee free, no credit card.