RACI matrix: a free template with a filled-in example.

The table that ends "I thought it was you." For each activity, who does it, who approves it, who weighs in, and who needs to know. Download the spreadsheet or build it directly in Tasskee.

Example: corporate website project Download it as a spreadsheet (opens in Excel and Google Sheets) or build it right in Tasskee, with deadlines, assignees and notifications.
Download spreadsheet Use it on Tasskee, free
ActivityProject managerDesignerDeveloperCustomerLeadership
Gather website requirements and goalsRCCAI
Define the page structureARCCI
Create the page layoutsARCCI
Approve the layoutRCCAI
Develop the websiteACRII
Write and review the copyACIRI
Test on mobile and across browsersACRI-
Approve publicationRICAI
Publish the websiteAIRII
Approve the change-order budgetR--CA

What is a RACI matrix

A RACI matrix is a table that crosses a project's activities with the people (or roles) involved and shows what role each one plays in each activity. The name comes from four letters: R for Responsible (who does the work), A for Accountable (who answers for the result and signs off), C for Consulted (who is asked before) and I for Informed (who is told afterward).

It is also called a responsibility assignment matrix. The payoff is direct: the doubt about who decides, who does and who needs to know goes away. The example above shows a company website project with five roles and ten activities.

How to fill it in, letter by letter

LetterWho it isRule of thumb
R (does the work)Whoever does the workAt least one per activity; there can be more than one
A (approves)Whoever answers for the result and gives the "okay"Exactly one per activity. Two A's mean no A
C (consulted)Whoever needs to weigh in before the decisionOnly people who actually change the decision; consulting too many slows things down
I (informed)Whoever needs to know the outcomeGets the information, doesn't weigh in; a notice is enough

The same role can hold both R and A on small activities. On others, the roles split: in "define the page structure," the designer does the work (R) and the project manager answers for the result (A). In "approve the layout," the manager drives the process (R), but the A is the client, because the client is the one who answers for the approval. This kind of decision is exactly what the matrix forces you to make.

Step by step to build yours

  1. List the project's activities as a verb and a result. Ten to twenty rows are enough; if you have more, group them.
  2. List the roles in the columns. Use job roles (manager, designer, client), not just names, so the matrix survives changes of people.
  3. Start with the A. In each row, first decide who answers for the result.
  4. Then the R, who does the work.
  5. Only then C and I. Ask: who needs to weigh in before? Who needs to know afterward?
  6. Review it with the team. Show the matrix to the people and confirm. An R that nobody knew they had turns into conflict in the middle of the project.

Common mistakes

  • Two A's in the same row. It looks democratic and, in practice, nobody decides. Pick one.
  • A row with no R. The activity exists, but nobody does it. Check the whole row.
  • Too many C's. If everyone is consulted on everything, the matrix becomes a permanent meeting. Consult whoever changes the decision.
  • Treating I as a meeting obligation. Informing means a message or an automatic notice, not an invitation.
  • Never updating it. When someone leaves the project or the scope changes, the matrix has to change.

When the template isn't enough

The RACI matrix says who is responsible for what, but not when. For that, pair it with a project schedule with dates, or with a 5W2H action plan when the focus is a list of actions. To understand the technique in depth, with variations such as RASCI and DACI, read the RACI matrix guide.

Another limit: the spreadsheet doesn't notify anyone. The C isn't asked to weigh in and the I receives nothing unless someone remembers to send the message. That is where RACI usually dies.

RACI inside the task

In Tasskee, each activity is a task with an assignee, and whoever approves or just follows along joins as an approver or watcher. Each role is notified at the moment it matters.

See the client portal

How to use the RACI matrix in Tasskee

  1. Add each activity from the matrix as a project task. The R becomes the task's assignee.
  2. Add the A as an approver and the C's and I's as watchers. Watchers and approvers are available from the Start plan.
  3. For the client who approves (the A in the example), invite them through the guest portal: they follow along, comment and approve without taking up a seat.
  4. If the approval needs a formal record, use an acceptance form with a simple electronic signature (name, IP, date and time, and hash), which records who approved and when.
  5. Use permission profiles to reflect the matrix: whoever is only informed can see the project but can't change it.

Want a ready-made delivery and acceptance record? See the delivery acceptance form template.

Frequently asked questions

RACI matrix FAQ

What does RACI mean?
There are four roles: Responsible (who does the work), Accountable (who answers for the result and approves), Consulted (who is consulted beforehand), and Informed (who is informed afterward). The matrix crosses activities with people or roles.
Can there be more than one A on the same row?
No. Each activity has a single A, the person accountable for the result. If there are two, no one is really accountable. The R, on the other hand, can be several people, and the same role can hold both R and A.
What's the difference between R and A?
The R does the work. The A decides whether it's done and is accountable for it. On a small activity, the same person can be both R and A; on a large one, the person who does it and the person who approves it are usually different.
When should you use a responsibility matrix?
When the project involves more than two or three people, different departments, or a client who approves stages. On a very small team, a 5W2H with the "who" defined is usually enough.
How does the RACI matrix become routine in Tasskee?
Each activity becomes a task with an assignee. Whoever approves is added as the approver and whoever just follows along as a watcher, and Tasskee notifies each one at the right moment.

Get your RACI out of the spreadsheet and put each role on the task.

Assignee, approver, and watcher on every task, with a notification at the right time. Try Tasskee free, no credit card.

15 days with everything unlocked No credit card Support in Portuguese
Contact us