RACI matrix: a free template with a filled-in example.
The table that ends "I thought it was you." For each activity, who does it, who approves it, who weighs in, and who needs to know. Download the spreadsheet or build it directly in Tasskee.
The table that ends "I thought it was you." For each activity, who does it, who approves it, who weighs in, and who needs to know. Download the spreadsheet or build it directly in Tasskee.
| Activity | Project manager | Designer | Developer | Customer | Leadership |
|---|---|---|---|---|---|
| Gather website requirements and goals | R | C | C | A | I |
| Define the page structure | A | R | C | C | I |
| Create the page layouts | A | R | C | C | I |
| Approve the layout | R | C | C | A | I |
| Develop the website | A | C | R | I | I |
| Write and review the copy | A | C | I | R | I |
| Test on mobile and across browsers | A | C | R | I | - |
| Approve publication | R | I | C | A | I |
| Publish the website | A | I | R | I | I |
| Approve the change-order budget | R | - | - | C | A |
A RACI matrix is a table that crosses a project's activities with the people (or roles) involved and shows what role each one plays in each activity. The name comes from four letters: R for Responsible (who does the work), A for Accountable (who answers for the result and signs off), C for Consulted (who is asked before) and I for Informed (who is told afterward).
It is also called a responsibility assignment matrix. The payoff is direct: the doubt about who decides, who does and who needs to know goes away. The example above shows a company website project with five roles and ten activities.
| Letter | Who it is | Rule of thumb |
|---|---|---|
| R (does the work) | Whoever does the work | At least one per activity; there can be more than one |
| A (approves) | Whoever answers for the result and gives the "okay" | Exactly one per activity. Two A's mean no A |
| C (consulted) | Whoever needs to weigh in before the decision | Only people who actually change the decision; consulting too many slows things down |
| I (informed) | Whoever needs to know the outcome | Gets the information, doesn't weigh in; a notice is enough |
The same role can hold both R and A on small activities. On others, the roles split: in "define the page structure," the designer does the work (R) and the project manager answers for the result (A). In "approve the layout," the manager drives the process (R), but the A is the client, because the client is the one who answers for the approval. This kind of decision is exactly what the matrix forces you to make.
The RACI matrix says who is responsible for what, but not when. For that, pair it with a project schedule with dates, or with a 5W2H action plan when the focus is a list of actions. To understand the technique in depth, with variations such as RASCI and DACI, read the RACI matrix guide.
Another limit: the spreadsheet doesn't notify anyone. The C isn't asked to weigh in and the I receives nothing unless someone remembers to send the message. That is where RACI usually dies.
In Tasskee, each activity is a task with an assignee, and whoever approves or just follows along joins as an approver or watcher. Each role is notified at the moment it matters.
See the client portalWant a ready-made delivery and acceptance record? See the delivery acceptance form template.
Who does it, approves it, is consulted, and is informed: rules, step-by-step guide, and example.
ViewWhat, why, where, when, who, how, and how much, with a filled-in example.
ViewStages, deadlines, assignees, and dependencies, with a system implementation example.
ViewThe essential fields to record that the client approved the delivery.
ViewThe client follows the project, comments and approves, without taking up a seat.
ViewA public link that becomes a task, ticket or signed receipt, in the right project.
ViewAssignee, approver, and watcher on every task, with a notification at the right time. Try Tasskee free, no credit card.