Delivery acceptance form: a free template with the fields that matter.

The acceptance form records that the client received and approved a deliverable. Download the spreadsheet with the fields and a filled-in example, or collect acceptance through a form in Tasskee, with name, IP, date, and time.

Example: acceptance of the Clínica Vida Plena website delivery Download it as a spreadsheet (opens in Excel and Google Sheets) or build it right in Tasskee, with deadlines, assignees and notifications.
Download spreadsheet Use it on Tasskee, free
FieldWhat to fill inExample
ProjectName of the project and of the contract the delivery belongs toClínica Vida Plena corporate website, contract 2026/014
CustomerLegal name and CNPJ of the recipientVida Plena Serviços de Saúde Ltda., CNPJ 12.345.678/0001-90
DeliveryWhat is being delivered, using the same name as in the scopePhase 2: 8-page website and booking form
Delivery dateWhen the client received it14/10/2026
Acceptance criteriaWhat was agreed for the delivery to be considered doneAll pages published, form sending email, working on mobile
Open items and reservationsWhat was left for later, if anythingBlog without the first 3 posts, which the client will send
Response periodHow many days the client has to accept or reject5 business days from receipt
Effect of acceptanceWhat the acceptance authorizes, like billing the installmentReleases invoicing of installment 2, R$ 6,000
Person responsible for acceptanceName and title of the person approving on the client's sideDr. Carolina Mendes, managing partner
Signature and recordHow the acceptance was signed and what was recordedElectronic signature on 10/16/2026, 10:42 a.m., with name, IP, and verification code

What is a delivery acceptance form

The acceptance form is the record that the client received a deliverable and agreed that it meets what was agreed. It closes a project stage, and is often what releases billing for the next installment. Without it, the conversation "I thought it wasn't ready" shows up right when it's time to get paid.

The form doesn't need to be long. It needs to be clear on four points: what was delivered, what was agreed as the definition of done, what remains pending and who approved, with a date.

How to fill it in, field by field

FieldWhat to writeCommon mistake
Project and clientProject name, contract number, legal name and CNPJ (Brazilian company tax ID)Citing only the project's nickname, with no way to find the contract
DeliverableWhat was delivered, using the same name as in the scope"Final delivery," without saying what it is
Acceptance criteriaVerifiable conditions: "published," "works on mobile," "sends email"A subjective criterion, like "looks nice"
Pending items and reservationsWhat was left for later, with a due date and an ownerAccepting "with minor adjustments" without listing which ones
Response deadlineHow many days the client has to accept or rejectHaving no deadline, leaving the acceptance open forever
Effect of acceptanceWhat the acceptance releases: an installment, the start of the next stage, the warrantyLeaving it implicit, and having a dispute when it's time to bill
Approver and signatureWho approves on the client's side and how the acceptance was recordedAcceptance given by someone without decision-making authority

Step by step to use the form

  1. Define the criteria before you start. Write in the scope what "done" means. At acceptance time, the form just repeats what was agreed.
  2. Send it along with the deliverable. The client receives the material and the form in the same email or link, with the deadline to respond.
  3. List the reservations. If the client points out adjustments, record each one with a due date. A partial acceptance is better than a dispute with no record.
  4. Keep the form with the project. When the contract is reviewed or a question comes up, the document has to be one click away.
  5. Avoid a single form at the end. One acceptance per stage avoids finding out at final delivery that the client never approved the layout.

Common mistakes

  • Verbal acceptance. "It's great" on a call proves nothing three months from now.
  • A vague criterion. If "done" isn't verifiable, the client can always ask for more.
  • A form with no date. Without the date, you can't count the response deadline or the warranty period.
  • Asking for acceptance from someone who doesn't decide. Check who can approve, which the project brief already records in the approvers block.

When the template isn't enough

The acceptance form records the approval of a deliverable, but it doesn't replace the contract. Clauses on penalties, warranty, intellectual property and termination call for a lawyer's review, and Tasskee doesn't provide legal advice. The template is a starting point for organizing the information, not a ready-made legal text.

To follow what happens between one deliverable and the next, use the weekly status report.

Acceptance on record, without hunting through email

In Tasskee, acceptance can be collected through a public form, with a simple electronic signature. Everything is kept together with the project.

See the forms

How to collect acceptance in Tasskee

Forms (Pro plan) can create a task or ticket, or collect a signed acceptance. The signature is a simple electronic signature and records the signer's name, IP, date and time, and a content verification code, the SHA-256 hash. It is not ICP-Brasil (Brazil's official digital certificate standard): if the contract requires a digital certificate, use a specific service for that.

  1. Create an acceptance form with the template's fields: deliverable, criteria, reservations and the acceptance text.
  2. Send the link to the client's approver at the end of each deliverable.
  3. Follow the form responses and, with the acceptance in hand, mark the stage as completed in the project.
  4. If the client follows along through the guest portal, they also comment and approve there, without taking up a seat on the plan.
  5. For projects billed by the hour, acceptance pairs well with the client closing statement: the closing statement gathers the hours up to the cutoff date, and the form records that the client approved what was delivered.

See other templates for the client relationship in the free templates hub.

Frequently asked questions

Acceptance form FAQ

What is a delivery acceptance form?
It's the document in which the client declares that they received a project deliverable and that it meets what was agreed. It marks the end of a phase and usually releases billing for the corresponding installment.
Is the acceptance form legally valid?
That depends on what was agreed in the contract and on applicable law, and Tasskee does not provide legal advice. The form is proof that the client approved the delivery, but for contracts and clauses, have a lawyer review it.
Is Tasskee's signature ICP-Brasil?
No. Acceptance collected through a form uses a simple electronic signature, which records name, IP, date and time, and a verification code (SHA-256 hash) of the content. It is not an ICP-Brasil digital certificate. If your contract requires that signature, use a service that issues it.
What if the client doesn't respond?
Define in the contract and in the form the response period and what happens with no answer, and have a lawyer review the text. The form should say this clearly so no one is surprised.
Can the acceptance include reservations?
Yes, and that's better. An acceptance with reservations records what's still pending and keeps the client from accepting generically and complaining later. Note each open item with a deadline and an owner.

Collect client acceptance by link, with a record of who approved and when.

In Tasskee, acceptance is a form with a simple electronic signature, linked to the project. Try it free, no credit card.

15 days with everything unlocked No credit card Support in Portuguese
Contact us